Attention:
If you have any questions, please contact us before commissioning or decommissioning.
Before initial commissioning, a setting time of at least 24 hours after refractory lining must be observed.
The following temperature curve must be observed during initial commissioning.
During decommissioning, the cooling rate must not exceed: 10/50 °C per hour (see curve).
During commissioning, the heating rate must not exceed: 10/50 °C per hour (see curve).